Predictive Schedule Optimization Framework for Aviation & Industrial Projects Using Constructability Driven Change Order Mitigation and Integrated Cost-Schedule Performance Modelling

Authors

  • M M Khan, M O Memon, M A Ul Haq, R Hashir Yousuf, M Umair Hammad Author

DOI:

https://doi.org/10.64180/

Keywords:

Schedule optimization; Constructability analysis; Earned value management; Change order mitigation; Cost-schedule integration; Aviation infrastructure; Industrial projects; Predictive scheduling; multi objective optimization; Project performance modelling

Abstract

Complex aviation and industrial projects experience substantial schedule and cost performance challenges, with ninety-eight percent of construction projects encountering cost overruns averaging eighty percent above baseline estimates. This research presents an integrated Predictive Schedule Optimization Framework combining constructability-driven change order mitigation, earned value management, and multi-objective optimization algorithms. 

Downloads

Published

2025-11-01

How to Cite

Predictive Schedule Optimization Framework for Aviation & Industrial Projects Using Constructability Driven Change Order Mitigation and Integrated Cost-Schedule Performance Modelling. (2025). International Journal of Engineering Fields, ISSN: 3078-4425, 4(4), 1-11. https://doi.org/10.64180/